IMO/VIN
Callsign
Flag
Service
Year
9311725
9VVN2
SINGAPORE
Tank Ship
2006
Activity#
Port
Date
Activity - Description
Deficiencies
7040123
Lake Charles, Louisiana
Aug 23, 20
Vessel Inspection - Agency Action Complete
7033015
STATEN ISLAND, New York
Aug 14, 20
Vessel Inspection - Approved Inspection
6894525
Houston, Texas
Jan 23, 20
Vessel Inspection - Approved Inspection
6894009
Houston, Texas
Jan 22, 20
Vessel Operational Control - Agency Action Complete
6852596
CORPUS CHRISTI, Texas
Nov 09, 19
Vessel Inspection - Administrative Action
6755334
New Orleans, Louisiana
Jul 19, 19
Vessel Inspection - Administrative Action
6646615
San Juan, Puerto Rico
Mar 28, 19
Vessel Inspection - Approved Inspection
6271670
CORPUS CHRISTI, Texas
Sep 20, 17
Vessel Inspection - Approved Inspection
6233197
Ponce, Puerto Rico
Aug 06, 17
Vessel Inspection - Approved Inspection
6136177
Houston, Texas
May 01, 17
Vessel Inspection - Approved Inspection
6100911
Cape Canaveral, Florida
Mar 08, 17
Vessel Inspection - Agency Action Complete
6098286
STATEN ISLAND, New York
Mar 03, 17
Vessel Inspection - Approved Inspection
5824898
San Juan, Puerto Rico
Mar 07, 16
Vessel Inspection - Approved Inspection
5157782
Jacksonville, Florida
Jun 27, 15
Vessel Inspection - Agency Action Complete
4799194
Houston, Texas
Feb 23, 14
Vessel Inspection - Approved Inspection
4801031
Houston, Texas
Feb 17, 14
Vessel Inspection - Approved Inspection
4500057
CORPUS CHRISTI, Texas
Dec 19, 12
Vessel Inspection - Approved Inspection
4299745
Houston, Texas
May 01, 12
Vessel Inspection - Approved Inspection
4257357
San Juan, Puerto Rico
Mar 07, 12
Boarding - Agency Action Complete
4257744
San Juan, Puerto Rico
Mar 06, 12
Vessel Inspection - Approved Inspection
4171807
Belfast, Maine
Oct 19, 11
Vessel Inspection - Approved Inspection
4112039
STATEN ISLAND, New York
Aug 11, 11
Vessel Inspection - Approved Inspection
1
0
System Subsystem Cause Construction/Loadline Structures
Description Due Date Resolved Void space gooseneck vents shall be fitted and designed IAW 46CFR30.10-25. Vessel's ballast tank vent flame screens on all ballast tanks have been penetrated, effectively disturbing the "30*30" mesh requirement, creating an explosion hazard. Certificate issuing authority to attest to proper flame screen construction installation. 50a Sep 11, 11 Yes
Resolved Date Resolution Oct 19, 11 Received paper work from the Owner''s which spoke with DNV, stating that since the ballast tanks on board the vessel have two fitted air vents / pipes, the above requirement does not apply.
Documents
Issued
Expires
Agency
Certificate of Compliance - Tank Vessel
June 27,2015
June 27,2016
Sector Jax
Classification Document
November 24,2015
January 7,2021
DNV
COC-TVE Annual
March 3,2017
March 3,2018
N/A
COC-TVE Renewal
March 7,2016
March 7,2018
N/A
International Load Line Certificate
April 19,2018
February 7,2021
DNV GL
International Oil Pollution Prevention Certificate
April 19,2018
February 7,2021
DNV GL
ISM - Document Of Compliance
October 17,2019
December 7,2024
DNV GL
ISM - Safety Management Certificate
April 8,2018
October 9,2022
DNV GL
Minimum Safe Manning Document
November 6,2014
SG
SOLAS Cargo Ship Safety Construction Certificate
May 9,2019
February 7,2021
DNV GL
SOLAS Cargo Ship Safety Equipment Certificate
May 9,2019
February 7,2021
DNV GL
SOLAS Cargo Ship Safety Radio Certificate
April 19,2018
February 7,2021
DNV GL
Tonnage Certificate, International
July 12,2010
DNV